Forestry

Edson Forest Products 2013


Sawmill rebuild, conversion


12 months duration


75 peak workforce

Deconstruction of existing sawmill. Supply of 300 tonnes of new fabricated structural steel.

Installation of structure:

  • Modification and reinforcements to existing buildings
  • New structural steel building additions
  • Onsite modifications of existing machinery support structure
  • New structural steel machinery support frames

Mechanical Installation of:

  • New debarker outfeed log sort conveyors and storage bin decks
  • New log singulating feeders
  • New Optimill canter with auto rotation scanning conveyor, double length skew slew and tilt infeed positioning conveyor, 4 sided canter, and inline vertical double arbour gang edger
  • Relocated optimised board edger with auto scanner and positioner
  • Relocated sideboard gang edger
  • New trimmer infeed board unscrambler
  • New and relocated residual conveyors system
  • Relocated and revised chip screening system
  • New hydraulic systems and piping
  • Start up and commissioning of new machinery

 


 

Edson Forest Products 2013


Planer mill rebuild, conversion from multi product processing plant to dimension lumber only processing.


12 months duration


75 peak workforce

Deconstruction of existing planer mill. Supply of 250 tonnes new fabricated structural steel

Installation of structure:

  • Onsite modifications of existing machinery support structure and building structural steel

Mechanical Installation of:

  • New package infeed and package breakdown machinery
  • New planer infeed layup line
  • New trimmer line
  • Relocate, extend and convert existing lumber sorter from J hook style to pusher lug style
  • Relocate and modify existing packaging line to suit dimension lumber
  • New hydraulic systems and piping
  • Modify existing residual conveyors and waste systems
  • Start up and commissioning of new machinery

 


 

Carrier Lumber - Prince George


New double line log infeed at sawmill


10 months duration


35 peak workforce

Installation of structural steel:

  • Installation of machinery support structural steel
  • Modifications and reinforcements to existing building structure

Mechanical installation of:

  • Tree length log decks
  • Log scanning infeed conveyors
  • Linden multi saw log merchandisers
  • Log sort bins and transfers
  • Nicholson double ring debarkers
  • Debarker outfeed transfer decks
  • Linden Step feeder log singulators
  • Canter infeed scanning conveyors
  • Relocation of existing canters
  • Installation of residual conveying system
  • 6" diameter mains compressed air piping system
  • Hydraulic piping systems
  • Start up and commissioning of new machinery